NI construction and building
NI construction output in early 2026 was 10% above a year earlier and housing 27% above. NI Water says around £7bn is needed for wastewater, and capacity limits decide where homes can connect.
The figures
Output by type of work, Q1 2026
Volume index, 2023 average = 100. Provisional.
Source: NI Quarterly Construction Bulletin, Q1 2026 (NISRA, 25 June 2026)
Change on a year earlier, Q1 2026
Percentage change in volume. Green is growth.
Source: NI Quarterly Construction Bulletin, Q1 2026 (NISRA, 25 June 2026)
NI emissions by sector, 2024
Net emissions 18.4 MtCO2e. The highlighted sector is the one this dashboard covers.
Source: NI greenhouse gas inventory 1990–2024 statistical bulletin (DAERA/NISRA)
Change since the base year
Percentage change in each sector, base year (1990 for most gases) to 2024. Red is a rise, green a fall.
Source: NI greenhouse gas inventory 1990–2024 statistical bulletin (DAERA/NISRA)
Rules on materials, land and connections
What applies to NI contractors, developers and merchants.
| Rule | When | What it means |
|---|---|---|
| UK CBAM | 1 Jan 2027 | Imported iron, steel, aluminium and cement of any non-UK origin, EU included (HMRC: no jurisdiction is exempt), once covered imports pass £50,000 in any 12 months; register by 31 Jan 2028 |
| EUDR (timber) | 30 Dec 2026 | First placers of wood and wood products on the NI market, micro and small businesses included (timber was already under the EU Timber Regulation; the 30 Jun 2027 date is for other products) |
| Contaminated land regime | Not commenced | Part 3 of the 1997 Order not in force; contamination handled through planning |
| Wastewater developer contributions | Voluntary scheme planned | Announced 19 March 2026; compulsory levy still under consideration |
Source: CBAM policy summary (HMRC, updated 2 November 2026); CBAM for Northern Ireland businesses (April 2026); EUDR application dates (European Commission); Deforestation-free products in NI (GOV.UK, updated 27 August 2026); Contaminated land (DAERA); Developer contributions for wastewater infrastructure (DfI Written Ministerial Statement, 19 March 2026)
Context
Wider figures behind the issue.
| Measure | Figure |
|---|---|
| Construction jobs, year to Sept 2024 | +2,040 (+5.5%) |
| Output vs pre-pandemic (Q4 2019), Q2 2026 | +17.5% |
| New dwelling starts, April to June 2026 | 1,502 (746 fewer than a year earlier) |
| New dwelling completions, April to June 2026 | 1,571 |
| UK emissions the built environment is directly responsible for | About a quarter (UKGBC, UK-wide) |
| Share of built environment emissions from construction and refurbishment | About a fifth (UKGBC) |
Source: NI Business Register and Employment Survey 2024 (DfE/NISRA, 8 October 2026); Construction output statistics, Q2 2026 (NISRA, 24 September 2026); Whole Life Carbon Roadmap FAQs (UK Green Building Council); NI Water update to Belfast City Council (NI Water, 28 January 2026); New dwelling statistics, Q2 2026 (DoF/NISRA, 19 August 2026)
Sources
Every figure on this page comes from these sources, checked on 20–21 October 2026; CBAM, timber, housing supply and release dates re-checked on 9 November 2026. Q3 2026 output figures are due on 14 January 2027. Figures marked "derived" are worked out from the published numbers. This is a dated snapshot: nothing is fetched or sent, and every chart can be downloaded as CSV.
- NI Quarterly Construction Bulletin, Q1 2026 (NISRA, 25 June 2026)
- NI greenhouse gas inventory 1990–2024 statistical bulletin (DAERA/NISRA)
- CBAM for Northern Ireland businesses (April 2026)
- Deforestation-free products in NI (GOV.UK, updated 27 August 2026)
- Contaminated land (DAERA)
- Developer contributions for wastewater infrastructure (DfI Written Ministerial Statement, 19 March 2026)
- NI Business Register and Employment Survey 2024 (DfE/NISRA, 8 October 2026)
- Construction output statistics, Q2 2026 (NISRA, 24 September 2026)
- Whole Life Carbon Roadmap FAQs (UK Green Building Council)
- NI Water update to Belfast City Council (NI Water, 28 January 2026)
- New dwelling statistics, Q2 2026 (DoF/NISRA, 19 August 2026)
- Carbon Border Adjustment Mechanism: policy summary (HMRC, updated 2 November 2026)
- EUDR application dates (European Commission, Access2Markets)
- NI construction bulletin, July to September 2026: release 14 January 2027 (GOV.UK)
Commentary: Focus on Construction & Building, 9 November 2026. More dashboards: all dashboards.